Reservoir reference
Gandikota Reservoir and the GNSS water network
Gandikota is a major Penna storage and a central junction in the GNSS water network. Krishna water reaches it through the Srisailam, Gorakallu and Owk corridor, then moves toward lift schemes, Chitravathi, Paidipalem and the lower GNSS reservoirs. Its history spans early proposals, major works in the 2000s, rehabilitation and the continuing effort to move water through the system quickly enough for Kadapa irrigation.

Reservoir reference
Reservoir at a glance
History
Key milestones
The dates below mark different stages of the project, from approval and construction to first storage, inauguration and later works.
-
1989Public record
GNSS enters the state budget story
The Andhra Pradesh budget described Galeru Nagari Sujala Sravanthi as a project conceived to extend irrigation and drinking water to drought affected areas. This establishes the scheme history before Gandikota became a major execution package.[6]
-
1996Public record
Budget allocation names Gandikota
The state Vote on Account listed ₹50 crore for Galeru Nagari and Gandikota Reservoir. This is an early budget record that names Gandikota directly.[7]
-
1999Public record
State records sanction to execute Gandikota
The 1999 budget speech said sanction had been accorded to execute Gandikota Reservoir with an irrigation objective of about 70,000 acres in Cuddapah district.[8]
-
10 Jun 2004
-
2004 to 2005
-
9 May 2009Land and R&R
YSR reviews Gandikota and Kadapa irrigation works
Dr. Y. S. Rajasekhara Reddy reviewed GNSS, Gandikota Lift Irrigation, Chitravathi, Pulivendula Branch Canal and other Kadapa works. The meeting also addressed rehabilitation of Gandikota displaced families.[10]
-
13 Aug 2009Construction
YSR seeks results on delayed irrigation works
At a state irrigation review, officials reported on GNSS Phase I, Gandikota Lift Irrigation, Gandikota to Chitravathi works and Lingala Canal. The Chief Minister pressed for completion and asked officials to deal considerately with displaced families.[11]
-
2012 to 2013Water and operation
Project material records completion of the dam works
Later feasibility material for the existing Gandikota reservoir describes the dam works as completed during 2012 to 2013. This is kept separate from the 2018 public inauguration milestone.[3]
-
By 2018
-
6 Jun 2018Land and R&R
Replacement road and bridge route opens
A replacement State Highway 31 route and high level bridge were required because the original alignment was affected by Gandikota submergence. The replacement route was inaugurated in June 2018.[2]
-
22 Sep 2018Water and operation
Gandikota Reservoir is inaugurated
The Government of India forest inspection record gives 22 September 2018 as the reservoir inauguration date.[2]
-
2018 to 2019Water and operation
Owk bypass completion and water supply are recorded
The state Socio Economic Survey reported that the Owk bypass tunnel was completed and water was supplied to Gandikota and other reservoirs in Kadapa.[13]
-
24 Jun 2020Public record
Major rehabilitation sanction supports fuller impoundment
The Water Resources Department sanctioned ₹522.85 crore for affected and displaced families in seven villages. The order linked the payment directly to the objective of impounding 26.85 TMC in Gandikota.[14]
-
2024 to 2027
Gandikota in the GNSS network
Gandikota stores water on the Penna and also serves as a major junction in the Galeru Nagari Sujala Sravanthi system. Krishna water reaches it from the Srisailam side through the right bank system, Gorakallu and Owk. From Gandikota, water can move toward Paidipalem, Chitravathi and the lower GNSS reservoirs. Its 26.85 TMC capacity is therefore only one part of its importance to Kadapa. [2][3][9][13]
Current irrigation planning also depends on how quickly water can be carried through the upstream system when Krishna flood flows are available. That makes conveyance capacity as important as the storage available at Gandikota. [15][16][17]
From proposal to a working reservoir
Gandikota appears in the irrigation record well before the Jalayagnam period. Andhra Pradesh budget records place Galeru Nagari in the state programme by 1989. A 1996 budget record names Gandikota in a combined allocation. In 1999 the state said sanction had been accorded for Gandikota Reservoir with an irrigation objective of about 70,000 acres in the then Cuddapah district. [6][7][8]
Implementation accelerated in the 2000s. GNSS Phase I received major administrative approval in June 2004 and state planning records show works under implementation in 2004 to 2005. Later feasibility material places completion of the dam works in 2012 to 2013. A Government of India inspection records the public inauguration on 22 September 2018. These dates mark different stages in the project. [1][2][3][9]
Expansion during the YSR government
Dr. Y. S. Rajasekhara Reddy’s government became a major implementation period for GNSS and the connected lift systems. In May 2009 he reviewed GNSS, Gandikota Lift Irrigation, Chitravathi, Pulivendula Branch Canal and other Kadapa irrigation works. A second review in August included GNSS Phase I, Gandikota Lift Irrigation and the Gandikota to Chitravathi works. [10][11]
Road replacement, village submergence, lift systems and command area works continued alongside construction. These works became part of the practical process of bringing the reservoir and its connected irrigation system into fuller use. [5][9][10][11]
Public record
Public money and project progress
Financial records come from different stages and parts of the project. Each row keeps the accounting category and project scope used by its source. For an annual budget entry, the administration shown is the government that presented the cited budget. The financial year itself may continue under a later government.
| Period | Record | Amount | Administration or record context | What the figure means |
|---|---|---|---|---|
| 1996 to 1997 | Budget allocation | ₹50 crore[7] | Andhra Pradesh. N. Chandrababu Naidu government at budget date. | Combined budget allocation for Galeru Nagari and Gandikota Reservoir. This is not a Gandikota only amount and it is not recorded expenditure. |
| Sanction period from 2004 to 2008 | GNSS Phase I sanction and expenditure position | ₹4,690.24 crore sanction. ₹3,630.30 crore expenditure[9] | Andhra Pradesh. Dr. Y. S. Rajasekhara Reddy government. | Whole GNSS Phase I, not Gandikota Reservoir alone. CAG records the sanction and expenditure position for the wider Phase I programme. |
| Position at 31 March 2013 | Cumulative expenditure position | GNSS ₹4,135.62 crore. GKLIS ₹717.63 crore. Gandikota to CBR lifts ₹1,386.75 crore[12] | Andhra Pradesh. N. Kiran Kumar Reddy government at reporting date. | CAG cumulative figures to 31 March 2013. They include expenditure incurred under earlier governments. The three figures cover different project lines and must not be added as a Gandikota Reservoir cost. |
| Position reported in the 2018 to 2019 survey | Ongoing project status snapshot reported in the 2018 to 2019 survey | GKLIS ₹983 crore administrative sanction. ₹735.71 crore expenditure reported. Gandikota to CBR lifts ₹1,744 crore administrative sanction. ₹1,519.35 crore expenditure reported[13][18][19] | Andhra Pradesh. N. Chandrababu Naidu government at reporting date. | Cumulative project status figures in the survey table. They are not approvals made in 2018 to 2019 and are not expenditure incurred only during that financial year. |
| 2020 | Rehabilitation and resettlement sanction | ₹522.85 crore[14] | Andhra Pradesh. Y. S. Jagan Mohan Reddy government at sanction date. | Payment for affected and displaced families in seven villages to enable impounding up to 26.85 TMC. |
| 2024 to 2027 | Annual budget estimates, not expenditure | GNSS canals and distributaries ₹2,552.62 crore in 2024 to 2025, ₹619.87 crore in 2025 to 2026 and ₹725.03 crore in 2026 to 2027. Shared rehabilitation heads were ₹148.01 crore, ₹36.01 crore and ₹36.01 crore[15][16][17] | Andhra Pradesh. N. Chandrababu Naidu government at budget dates. | Kadapa irrigation budget heads. The rehabilitation head covers Gandikota villages together with PBC villages. These are budget estimates and must not be described as Gandikota only expenditure. |
About these figures: Administration names are used only when a cited record can be tied to one government. Records that span more than one government, or come from a later audit or project estimate, are labelled by their record context. Budget estimates, sanctions, agreement values and cumulative expenditure are separate accounting measures and are not totalled.
Dam, storage and spillway
Project feasibility material gives Gandikota a Full Reservoir Level of 212 metres and a Minimum Drawdown Level of 202.9 metres. Gross storage is about 760.30 million cubic metres, equal to 26.85 TMC. The 2021 feasibility report lists live storage at 669.38 million cubic metres, about 23.639 TMC, with dead storage of 90.93 million cubic metres. The 2025 Central Water Commission dam register lists live storage at 631.465 million cubic metres, about 22.30 TMC. The two official publications use different live storage figures, so both are identified by source. The feasibility report also gives a water spread of about 10,773.89 hectares at Full Reservoir Level. [3][4]
The feasibility report describes a concrete lower dam about 320 metres long at the top and about 25.2 metres high from river bed level. The CWC register records 325 metres and 25 metres. Both sources give a designed spillway capacity of 8,180 cubic metres per second. The feasibility report describes a free flow ogee spillway with 14 bays. The spillway allows Gandikota to handle flood flows on the Penna as well as store water. [3][4]
Krishna water route to Gandikota
Transferred water reaches Gandikota from the Srisailam side through Gorakallu and Owk. The Government of India GNSS inspection records the flood flow canal from the Owk foreshore toward Gandikota as completed and carrying Krishna water. [2][3]
Gandikota also receives natural basin inflow, including contribution from the Chitravathi River recorded in project feasibility material. A separate lift system carries stored water in the opposite direction from Gandikota toward Chitravathi Balancing Reservoir. [3][9]
Distribution beyond Gandikota
The Gandikota Lift Irrigation Scheme moves water toward Paidipalem and the Pulivendula side. Another staged lift system carries water toward Chitravathi Balancing Reservoir. Farther down the GNSS chain, Vamikonda and Sarvaraja provide smaller balancing and distribution storages. Together these reservoirs show how water moves from a large regional storage into local irrigation networks. [3][5][9][13]
Rehabilitation and full storage
Fuller impoundment at Gandikota required road replacement and rehabilitation in villages affected by submergence. In June 2020 the Water Resources Department sanctioned ₹522.85 crore for affected and displaced families in seven villages. The government order linked the payment with the objective of impounding the reservoir up to 26.85 TMC. [2][14]
By this stage the dam structure, rehabilitation, roads, canals and downstream systems had their own timelines. That is why the Gandikota record includes several dates for different parts of the project. [2][5][14]
Current operating priority
Recent state outcome budgets continue to list faster movement of Srisailam water to Gandikota as a Kadapa irrigation priority. The focus is on moving water through the upstream system while it is available and then distributing it from Gandikota into the connected command. [15][16][17]
Water network
Where this reservoir sits in the system
Evidence
Sources and what they establish
The numbered references used throughout the page are listed below. Government records and official water data are used wherever available. Contemporary reporting is included when it documents an event that is not covered by those records.
- Tier 1 · Official government record[1] Government of Andhra PradeshAnnual Plan for Galeru Nagari Sujala SravanthiUsed for: GNSS start period and irrigation project backgroundView source
- Tier 3 · Official technical or environmental record[2] Ministry of Environment, Forest and Climate ChangeGNSS Phase I forest clearance site inspectionUsed for: Phase I approval, reservoir capacity, Full Reservoir Level, State Highway 31 replacement and 2018 inaugurationView source
- Tier 1 · Official project report[3] NREDCAPGandikota Pumped Storage Project feasibility materialUsed for: natural basin inflow including Chitravathi River contribution, transferred Srisailam water reaching Gandikota and reservoir supply rolesView source
- Tier 2 · Official water data[4] Central Water CommissionNational Register of Specified Dams 2025Used for: dam register engineering and completion metadataView source
- Tier 1 · Official government record[5] Government of Andhra PradeshAnnual Plan 2016 to 2017. GNSS, Gandikota and rehabilitation statusUsed for: GNSS objectives, Gandikota and Paidipalem transfer role, submerged villages and rehabilitation progressView source
- Tier 1 · Official government record[6] Government of Andhra Pradesh, Finance DepartmentBudget speech 1989 to 1990Used for: early GNSS conception in the state budget recordView source
- Tier 1 · Official government record[7] Government of Andhra Pradesh, Finance DepartmentVote on Account budget 1996 to 1997Used for: Rs 50 crore combined allocation for Galeru Nagari and Gandikota ReservoirView source
- Tier 1 · Official government record[8] Government of Andhra Pradesh, Finance DepartmentBudget speech 1999 to 2000Used for: sanction to execute Gandikota Reservoir and the stated 70,000 acre irrigation objectiveView source
- Tier 3 · Audit record[9] Comptroller and Auditor General of IndiaPerformance audit of Jalayagnam, 2012Used for: GNSS Phase I sanction and expenditure context, plus the staged lift route from Gandikota toward Chitravathi Balancing ReservoirView source
- Tier 5 · Reputable journalism[10] The New Indian ExpressKadapa irrigation review, 9 May 2009Used for: Dr. Y. S. Rajasekhara Reddy review of Gandikota and connected irrigation works and the rehabilitation direction reported at the meeting. Any financial figure in the report is treated as a reported statement unless independently supported.View source
- Tier 5 · Reputable journalism[11] The New Indian ExpressState irrigation review, 13 August 2009Used for: Attributed statement by Dr. Y. S. Rajasekhara Reddy and contemporaneous reporting that the review included GNSS Phase I, Gandikota Lift Irrigation and Gandikota to Chitravathi works.View source
- Tier 3 · Audit record[12] Comptroller and Auditor General of IndiaState Finances report for 2012 to 2013Used for: cumulative expenditure at 31 March 2013 for GNSS, Gandikota Lift Irrigation and Gandikota Reservoir to CBR lift schemesView source
- Tier 1 · Official government record[13] Government of Andhra Pradesh, Finance DepartmentSocio Economic Survey 2018 to 2019Used for: ongoing project status values reported in the 2018 to 2019 survey, including administrative sanction, expenditure position, physical progress, Owk bypass completion and water supplied to GandikotaView source
- Tier 1 · Government Order or Gazette[14] Government of Andhra Pradesh, Water Resources DepartmentG.O.Rt.No.323 dated 24 June 2020Used for: Rs 522.85 crore R and R sanction for seven Gandikota villages to enable impounding up to 26.85 TMCView source
- Tier 1 · Official government record[15] Government of Andhra Pradesh, Finance DepartmentOutcome Budget 2024 to 2025, Irrigation Projects KadapaUsed for: current carrying capacity strategy, GNSS canals and distributaries budget head, Gandikota R and R head and Owk tunnel budget headView source
- Tier 1 · Official government record[16] Government of Andhra Pradesh, Finance DepartmentOutcome Budget 2025 to 2026, Irrigation Projects KadapaUsed for: continued carrying capacity strategy and 2025 to 2026 GNSS, Gandikota R and R and Owk tunnel budget headsView source
- Tier 1 · Official government record[17] Government of Andhra Pradesh, Finance DepartmentOutcome Budget 2026 to 2027, Irrigation Projects KadapaUsed for: continued carrying capacity strategy, 2026 to 2027 GNSS canals and distributaries, Gandikota rehabilitation and Owk tunnel budget headsView source
- Tier 1 · Parliamentary record[18] Parliament of India, Rajya SabhaUnstarred Question No. 620, 14 July 2014Used for: start years and likely expenditure reported up to 2011 to 2012 for Gandikota Lift Irrigation and Gandikota to CBR Lift Irrigation SchemesView source
- Tier 1 · Official government record[19] Government of Andhra Pradesh, Planning DepartmentSocio Economic Survey 2017 to 2018Used for: the ₹1,744 crore Gandikota to CBR lift project value already reported before the 2018 to 2019 survey and the stated direction from Gandikota to Chitravathi Balancing ReservoirView source